What is Actuals in Schedule options
Forum Sponsor
Top Posters
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Hunais M J
0 posts
Soheil Barekat
4 posts
henrigpc
0 posts
Hashil Ali
0 posts
Hi,
I am currently migrating from P3 to P6. In one of our reports - Variance Analyis in P3 filter I can define the filter the following:
if Actual dates Is WR DD-30D DD+0D
where Low Value = DD-30D
High Value = DD+0D
In P6 the Actual dates is not there... it was changed to something. I tried to use the Planned Start or the Actual Start but the result was different than I expect. Can you help with this? Thanks.
Regards,
quartz
Hi,
I am currently migrating from P3 to P6. In one of our reports - Variance Analyis in P3 filter I can define the filter the following:
if Actual dates Is WR DD-30D DD+0D
where Low Value = DD-30D
High Value = DD+0D
In P6 the Actual dates is not there... it was changed to something. I tried to use the Planned Start or the Actual Start but the result was different than I expect. Can you help with this? Thanks.
Regards,
quartz
Progress override means ignore the logic while Actual dates is not but using actual date when calculating forward pass and backward pass. Below is example of the difference.
