Weight

R
Rodel Marasigan 👤 Member for 19 years 7 months

Hi David,



Is your Program cost loaded? If it is just spread the cost to each 4 activities with that weightings and P6 will calculate base on the weighting you allocated.

Alternatively if you don’t want to affect the cost you can use this method.



Under Project Window-> Calculation tab-> Default Price/Unit for Activities without resource or role Price/Unit enter $1 or $0.01 (less value much better so cost will show as zero rounding but actually it will record up to the last digits in the background)

Under Activity Window-> Status tab change labor unit to labor cost and enter the weightings as per sample below.

Rev1 = $0.06

Rev2 = $0.01

Rev3 = $0.01

Rev4 = $0.02

or Use Top Down Estimate

If you need more understanding click link below as it was explain further to this forum.

Weightings Post #2

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts