Planned Value

R
Rodel Marasigan 👤 Member for 19 years 7 months

Dinesh,

Of course Plan Value will keep changing once you update the Project. Plan Value will not change if you have assigned a baseline and use BL Plan Value. For current project all activities that not happened on the plan date will move after the data date therefore the plan values will also move. The use of baseline is to compare what has been targeted vs the current. Current Plan Value will become a forecast to complete.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts