Price / Unit allocation in Roles........
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Haresh,
You can define as many rates in roles but you can only use 1 at the time. If you want to use Price/Unit 2 or 3 etc…, you need to change the settings in Project Window under Resources tab-> Assignment default then change Price/Unit by clicking drop down box selection to any rates you wanted to use before adding new roles assignment.
The reason why your budget remains zero is your rate source still using resource instead of roles. If using roles rate you need to change the rate source to role. You may also need to refresh the cost by select Tool-> Recalculate Assignment Cost. I have explain 3 option of how to use different rate in P6 (click link below)
Cost coding of Activities Post #29
If it is not clear to you let me know so I can help you further.