Overallocated Early Units
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Dan,
If you have a parallel activities using same resource and your max unit/time is only 8 (for example) and both activities using 8hrs/day per resource then 8hrs will be over allocated. You can level your resource but it might push your activities. Another way is to increase your max unit/day to max resources that your going to use per day.
Another cause is if max unit/day =8 and duration is =5days but resource is 50 unit then it equals to 10hrs/day. Resource profile will show 2hrs/day over allocated.