resource reports- hourly distribution

A
Alaa Al haj 👤 Member for 18 years 7 months
R
Rodel Marasigan 👤 Member for 19 years 7 months

Arnold,

You don’t need to change the duration format, and it will work as long as the resource analysis is in hour.



Alaa,

How many hours per day are they working? Are you using shift/day?

You can organize your resource by WBS level 4 then Resource then Start. Under Start group interval change to day as shown below

Group & Sort

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Alaa,



Go to Resource Assignment and Group it by Resource ID or Name.



Regards,



Arnold

A
Alaa Al haj 👤 Member for 18 years 7 months

thanks arnold

actually here I have 2 problems

1- I want to see all resources fro each unit separately



2- the resource distribution in hour



I will try what you advice and get back to you

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Alaa,



Is your Original Duration is in Hour? Otherwise, if not the resource distribution will be in days.



Change the Day into Hour. Go to Edit --> User Preferences --> Time Units Tab, "Units & Durations Format". Similarly, change the Resource Analysis from Day to Hour.



When done, try to adjust the Timescale, Date Interval to "Day/Hour".



Regards,



Arnold

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts