Commencement Date

R
Roger Booth 👤 Member for 19 years 7 months

Check your calendar. If the calendar is a 5 day week and the commencement date is at a weekend, it will show float equal to the duration until you start work on the Monday

M
moutaz aldeib 👤 Member for 22 years 5 months

Dear Ali,



The problem is that the commencement date should have TF=0 and linked to the critical activities which have TF=0, also in the schedule report I have found "Milestone with invalid relationship"



Regards

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts