Check your calendar. If the calendar is a 5 day week and the commencement date is at a weekend, it will show float equal to the duration until you start work on the Monday
Dear Ali,
The problem is that the commencement date should have TF=0 and linked to the critical activities which have TF=0, also in the schedule report I have found "Milestone with invalid relationship"
Regards
so where is the problem?