HOW to update the program?

M
Michael Tandog 👤 Member for 16 years 1 month

last hirit kabayan paano mag input nang resources? nakalimutan ko na yung tinuro sa akin sa clase namin..



thanks,



michael

R
Rodel Marasigan 👤 Member for 19 years 7 months

Steps creating baseline of current project.

1)     Select Project-> Maintain Baseline

2)     Click Add then tick “Save a copy of the current Project as new baseline" then click Ok

3)     Once the baseline is created – click close

4)     Select Project-> Assign Baselines

5)     Click Project Baseline drop down box and select the baseline you just created then click Ok

6)     Select Enterprise Project

7)     Click or highlight your Project then under Project Details-> Settings tab make sure that Project Baseline is selected or tick.



You have now baseline attached and can start updating the program.

R
Rodel Marasigan 👤 Member for 19 years 7 months

Hi Michael,

Be specific to your query so everyone can help you out. Do you want to copy your baseline and use to update the program or what?

M
Michael Tandog 👤 Member for 16 years 1 month

Yes, Kabayan I need your help because i’m only new using P6. I have only baseline programme without resources how to update on that ? from baseline to current update?



thanks!

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts