Quick way to Link activities

A
Ali Farhat 👤 Member for 17 years 7 months

I think I got the idea...

having two relationships between same activities reflects the actual logic. maybe i considered it not logical because only one realtionship type actually drives the dates while the other does not effect.

R
Rodel Marasigan 👤 Member for 19 years 7 months

Ali,

The normal usage for that is “A” SS “B” and “A” FF “B” meaning “B” cannot start until “A” started and “B” cannot finish until “A” is finished which is common in construction especially if your activities is not breakdown to the lowest detail.

Ex: Wall Partition.

You cannot start Electrical rough-in without starting wall framing but you can’t finish electrical rough-in without finishing wall framing before wall cladding (not always the case). In some other cases other combination is also use for high level activities.



Primavera default is FS which keep adding until you meet all four linking process.

A
Ali Farhat 👤 Member for 17 years 7 months

Rodel,



I am aware of that...what i meant is two relationships between the same activities..

if A is related to B with a FS relation and you link them AGAIN, primavera will assume a second relationship between A and B. Now you will have A and B linked by FS and FF.

this is what i was refering as not logical...to me at least

R
Rodel Marasigan 👤 Member for 19 years 7 months

Ali,

It’s common sense. Imagine if you have only one relationship on each task from beginning to end. All you activities are lying on one path which is all critical. How long are you going to finish a project if one task needs to finish first before starting the new task? There a lot of task that can run in parallel after a trigger task is finished or even just started.

Simple Ex: Concrete foundation

Once the IFC drawing is release, you can excavate and fabricate the rebar and formworks at the same time. You don’t need to wait excavation finished before fabrication of rebar unless that area is impossible to installed fabricated rebar and requires in situ.

Another are some roughing electrical and plumbing that need to embed before pouring of concrete. It runs parallel with rebar and formworks.

Now you can answer you own question.

A
Ali Farhat 👤 Member for 17 years 7 months

Speaking of which....why primavera adds multiple relationships??? i find this stupid. i think they should include an optioon not to allow adding double relationship

or is there any hidden logic behind that

please advice

Regards

R
Rodel Marasigan 👤 Member for 19 years 7 months

Hi Mike,

I know and I assumed that’s the case as he mentioned that it was consecutively order according to activity id. Thanks

M
Mike Testro 👤 Member for 20 years 6 months

Hi Rodel



To do this you have to be certain that they are in the correct order when you highlight them.



Best regards



Mike Testro

R
Rodel Marasigan 👤 Member for 19 years 7 months

Farzin,

Highlight all activities that need to link from 1st to last then select Edit-> Link Activities

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts