Resource Curve ISSUE in P6

R
Rodel Marasigan 👤 Member for 19 years 7 months

Suresh,

You can also use level of effort link from first and last activity of a period if summary task is not possible. (Ex: activities are sitting on different WBS)

D
David Blades 👤 Member for 22 years 2 months

Hi Suresh



I do this on occasion by creating a ’level of effort’ activity for the entire duration; link start to start to your first activity in April and link finish to finish to your last activity in June, both relationships should be under ’predecessor’. Assign your 10 engineers to this level of effort activity and I think this may solve your problem. - Worth a try!



I hope this helps

M
Mike Testro 👤 Member for 20 years 6 months

Hi Suresh



Try putting the resource on a summary bar.



Best regards



Mike Testro

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts