You can also use level of effort link from first and last activity of a period if summary task is not possible. (Ex: activities are sitting on different WBS)
Hi Suresh
I do this on occasion by creating a ’level of effort’ activity for the entire duration; link start to start to your first activity in April and link finish to finish to your last activity in June, both relationships should be under ’predecessor’. Assign your 10 engineers to this level of effort activity and I think this may solve your problem. - Worth a try!
I hope this helps
Hi Suresh
Try putting the resource on a summary bar.
Best regards
Mike Testro