Duration of Activity & Resource not coming same!!!!!

R
Rodel Marasigan 👤 Member for 19 years 7 months

John,

The only way to check that is on Activity Window-> Activity Detail-> Resources tab

Right Click and select customise resource column then under duration double click Original duration, under dates double click Planned Start and Planned Finish. Your planned date duration maybe originally 9.56 but change to 10 but your settings in Project Window-> Detail-> Calculation tab-> Activities (link Budget and At Completion for non started Activities is not tick)

Note: Don’t forget to show the time.

J
John Paul Augustine 👤 Member for 16 years 3 months

Actually I am having activities. for example



Acivity ID----------Original Duration-------------- Activity Name

Sub001-------------------10 Days----------------------Substructure



I asssigned resources(BOQ pay items) for this activity for example.

Excavation - 100m3

Backfilling - 50 m3

This is what showing in gantt chart.

But in my resource assignments window duration for the above resources showing as follows

Resource Name--------- Original Duration-----Budeget Quantity

Excavation----------------------9.56 Days-------------100 m3

Backfilling ------------------------10 Days--------------50 m3



Why the duration for the resources & Acivity duration coming differnt in the above case?




R
Rodel Marasigan 👤 Member for 19 years 7 months

What do you mean not coming the same? Is the resource unit the same as activity duration * remaining Unit/time?

Can you elaborate more?

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts