Comparison between Baseline & Actual

R
Rodel Marasigan 👤 Member for 19 years 7 months

Planned progress = Schedule % complete in Primavera. If you want to display the %complete on bar then click the Bar icon. Tick the baseline you want to show (Project BL, Primary BL...etc) While highlighted the selected baseline click the bar level tab. Click add and select where you want it to be display (i.e. Right, Left, Center..etc) then Select Schedule % Complete. Do the same on Actual Bar and select Activity % Complete.



This should display the % Complete on each bar

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts