necking bar for suspended activty in P6??

L
Lucas l 👤 Member for 16 years 3 months
R
Rashid Iqbal 👤 Member for 16 years 2 months

The best way to handle such activities is to split them as the projetc progresses. Change the description as well to indicate the work that actually happened during that period.



Regards

Rashid

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Lucas,



In your case, you can create and assign a calendar identifying all the suspended dates as nonwork.



Regards,



Arnold

L
Lucas l 👤 Member for 16 years 3 months

Ian, Thanks for your answer.



For my case, the activity is suspended for multiple time, can that be represented in P6?



I can only suspend the activity once.



Regards

Lucas

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts