necking bar for suspended activty in P6??
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
The best way to handle such activities is to split them as the projetc progresses. Change the description as well to indicate the work that actually happened during that period.
Regards
Rashid
Hi Lucas,
In your case, you can create and assign a calendar identifying all the suspended dates as nonwork.
Regards,
Arnold
Ian, Thanks for your answer.
For my case, the activity is suspended for multiple time, can that be represented in P6?
I can only suspend the activity once.
Regards
Lucas
You can neck a suspended bar by going to the bar setup menu, go to the Bar Settings Tab and check the box for Bar Necking for Activity Non-work intervals.
Ian
http://www.emerald-associates.com