What is the best/simpliest way to add cost to the sched

Z
Zq qz 👤 Member for 23 years

If your familiar with P3 . Do it in P3 then export it to P6.

J
John Goulden 👤 Member for 23 years 6 months

You have two hopes - Bob Hope and no hope.



We tried to set up Contracts Manager to take progress data from P6 to pay the contractor via an operational BofQ aligned to the activities in the programme. All of which can be done if you believe the manual. We stopped when our heads started to hurt.



P6 wants binning.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts