Early Start

Z
Zq qz 👤 Member for 23 years

Option 1 is the best solution. THAT’S PLANNING WORK......Avoid shortcuts.

A
Anbin Ponnith 👤 Member for 17 years

Dear Gary,



Thanks for the reply...



I used the first option.I changed the relationship and submitted the report.



My Client is not allowing to schedule with the second option.



Is there any other way other than adjusting the out of sequence activities.(but not using project override).



With Thanks & Regards,



Anbin Ponnith

G
Gary Whitehead 👤 Member for 17 years 2 months

Most likely Activity A23R1SA01 has a predecessor which is not yet complete, ie you have out of sequence working.



2 options:

1) Correct the logic to show the true sequence (best practise)

2) Go to tools, schedule, schedule options, and select "progress overide" instead of "retained logic" (easiest)

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts