Probably the easiest is to use the Resource Usage Spreadsheet and copy/paste it into Excel and then make a graph in Excel.
You can also use the Resource Assignments Module and copy/paste from there or make a time phased resource loading report and save it as a csv which can be opened with Excel.
Ian
http://www.emerald-associates.com