David,

do you mean that it is not possible to input a time-based cost or expense, say: the cost of a work-team during a four week task, against the corresponding "Budget Log" period?

what is it for in that case?

Alexandre

D
David Kelly 👤 Member for 21 years 8 months

No. The budget figure does not "spread" you have to do it manually, i.e. the spending/benefit plan.