Append P6 and MS Project Schedules

R
Robert Mellalieu 👤 Member for 23 years 6 months

You can always use the File import project mpp function from Primavera. This does work however is fraught with anomalies such as calendar mismatches, task type interpretation etc. A better option is to import MSP into Pertmaster and then export it to Primavera. This method has a lot less hang-ups, sometimes it is even accurate. Either way you must check the schedule after.

Good Luck

A
Alex Dale 👤 Member for 16 years 5 months

So what I’m currently having to do is to save a Primavera programme as an excel sheet. Then amend it with the activites from the Project file. I then have to do the logice work manually. This is the fastest route I have found so far but only really helps with importing the activites and IDs, not any costs or resources.



I’m still searching for the elusive answer af making the two systems compatible.



Hope this helps a little.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts