MIlestones with invalid relationships...
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Thanks again, Dieter
Analysing the relationsships and the schedule log during trial and error, Ive so far come to the following results:
1) When a start milestone (succ.) is linked from a start milestone (pred.), the only available options of links are FS or SS, however, the schedule log will report "invalid relationship" when FS, but not on SS.
2) When a finish milestone (succ.) is linked from a finish milestone (pred.), the only available options of links are FS or FF, however, the schedule log will report "invalid relationship" when FS, but not on FF.
3) When a start milestone (succ.) is linked from a finish milestone (pred.), the only available options of link is FS.
4) When a finish milestone (succ.) is linked from a start milestone (pred.), the only available options of link are FS or SF. The schedule log does not report any errors no matter which one is utilized.
Havent yet investigated if lead/lags have any impact on the above, however, the above have worked for me so far.
Regards,
Bo
Bo
For Start and Finish Milestones not all types of relationships are possible.
But in my opinion:just ignore these warnings. I never realized any bad impact onto the schedule due to these "wrong" relationships.
Regards
Dieter