open you current project (monthly update) and baseline project at the same time. Then export them into XER format, a XER will be created with two projects inside
before we were taking the back ups of monthly updations and keeping it in the Back up folder.When ever our top management needs the monthly updated program.We were sending the updated program of particular month along wit h the base program.Is this possible in P6.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
open you current project (monthly update) and baseline project at the same time. Then export them into XER format, a XER will be created with two projects inside
Hi Arun,
If you export the .XER file along with the baseline, only the current open project will be exported. The baseline will stay in your project.
You can do one thing, keep a copy of a baseline in your folder, then what you need only is to export the monthly updated programme.
It means you need to send them individually.
Regards,
Arnold
Hai Arnold
Thxs
Again my qurie is
before we were taking the back ups of monthly updations and keeping it in the Back up folder.When ever our top management needs the monthly updated program.We were sending the updated program of particular month along wit h the base program.Is this possible in P6.
With regards
Arun.V
Hi Arun,
You mean back up a project. If yes, then go to File Menu --> Export --> Primavera PM/MM - (XER).
http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=67775
If database, then it is a long story... Anyway, I highly recommend to read the Primavera Manual.
Regards,
Arnold