I understand that starting with version 6.2 of P6 that unless P3 is already installed when P6 is installed, then the button for importing and exporting p3 is grayed out. 

If P3 was installed when you installed P6, then I would suggest that you get help from Oracle (good luck).  I don't know why Oracle has to make it difficult.

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Robin,



I think you don’t have the users access privilege to import P3 project.



Regards,



Arnold

R
Robin Kilmister 👤 Member for 19 years 2 months

Hi Yasser,



I have read your thread but I do not have the same problem as you.



I have P3 installed on my machine.



I do not get the choice to even import the P3 plans to P6 as the choice toggle is greyed out on the import tab. I think that there is an internal switch on the P6 programme that needs checking or I do not have compliant software for the import?



Cheers



Robin

Y
Yasser Elyosefi 👤 Member for 21 years 3 months

Hello Robin,



Revert to my thread titled

" P6 Ver. 7 bug when importing from P3 "



It is a software bug in V7 as well as V 6.2



Regards,



Yasser

Y
Yasser Elyosefi 👤 Member for 21 years 3 months

Try not to use the backup files.



USE the folder into which the P3 files are copied (from copy function not Backup)

Forum Sponsor

Top Posters

GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts