Hi Alaa,
Assign first the resources into your activities in Primavera window. When done, export the activities with Resource ID to Excel.
In Excel sheet you can assign the quantity by using the vlookup function with a Lookup_value equal to your Activity ID.
If ever, you cannot follow my steps, email me at [email protected]
Regards,
Arnold
Thanks Arnold,
I try this solution but the problem is I have 3000 activities and I can’t assign resources to all activities in primavera (it will take me very long time) so I just want to ask if it is possible to export activities and resources as table (matrix)
Like
AD RESOURCE 01
RESOURCE 02 RESOURCE 03 RESOURCE 04 RESOURCE 05
A1000 20 25 17
A1001 7 33 40
A1002 60 20 5
A1003 30 30 60
THIS IS ASAMPLE OF WHAT I WANT THE PRIMAVERA to DO (OF COURSE AFTER CREATING RESOURCES IDs
Thanks
Alaa