Progressing and resource loaded activity

D
David Kelly 👤 Member for 21 years 8 months

Brian,



In P6, reducing remaining duration means that you are increasing the "Duration % complete"



So, the easy (!?) answer is that "Recalculate actual units and costs when duration % complete changes" is ticked in the "Calculations" tab at the project level.......