Progressing and resource loaded activity
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Brian,
In P6, reducing remaining duration means that you are increasing the "Duration % complete"
So, the easy (!?) answer is that "Recalculate actual units and costs when duration % complete changes" is ticked in the "Calculations" tab at the project level.......