Integration of the program

A
Anand Porle 👤 Member for 16 years 8 months
R
R. Catalan 👤 Member for 20 years 10 months

Anand,



After adding the project to the Master Programme, you have to do the linkage/activity relationships manually, then run.



The next import action shall be "Update Existing Project", then run to check the changes on the sub-project and Master Programme.



Best regards,

R. Catalan

A
Anand Porle 👤 Member for 16 years 8 months

Hi Arnold



you have got what i mean. but still one mor step i need to know.

1) i just import that to the Master plan where WBS levels are defined.

2) Once i import them how do i do the interface / link them correspondingly to have over all comparision or final result.



Regs



Anand

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Anand,



If I understood your question correctly, you need to create first a project as your Master Plan. In order to build the Master Plan try to gather those data from the Contractor and import all of these. During the import "Import Action" select "Add Into Existing Project".



Regards,



Arnold

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts