Budgeted Units were Multiplied by 8
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi Arnold,
That worked, Thank you.
Dinesh
Hi Dinesh,
In addition to Anoon info.
According to you that all Budgeted Units were multiplied by 8. If you are using P6 it means that your setting in Edit --> User Preferences --> Time Units tab, "Unit of Time" is in "Hour" just change it to "Days".
Regards,
Arnold
thats the difference between the planning unit used; it may be in Hours or in Days...
Hello,
You can simply correct the budgeted units by performing a global change. You must be able to filter on the activities needing the change. If interested, let me know & I can walk you through.
Jason