Hi Arnold...Thanks for answer me...my second question was fixed but the problem was that...Activate the filter to all activities in...Edit - Filters - All Activities....because P6 had active "2 week lookahead" filter active by default...so...i fixed...



mmmjjj in my first question...i’ll take your information to review and fix the problem if the cause if that you told me.



THANKS....A LOT....

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Jhorbam,



1. The relationship with dotted line is the "Non-Driving Relationships". Relationship is depends on the logic or sequence of your work. If how are you going to link your activities in a logical way.



In order to fix this you need to change the logic. Non-driving Relationship, frequently happen when your "Free Float" is not equal to zero.



2. I think you need to check your WBS Level / Activity Code if it is "Collapse All or Collapse To" Mode. Try to Expand your WBS Level by going to View --> Expand All. I am not sure but give a try.



Regards,



Arnold


Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts