Hi Richu,
I got the same dilemma with you. What I do is delete or hide those activities since it will become redundant when you organize using WBS grouping. I also renumber the activities using global change facilities.
I usually import MSP project just to save time typing and use it in further detailing this MSP schedule using P6 capabilities.
Probably other PPers has better method , kindly share or later version of P6 will have this facilities.
Regards,
Ronald