Resource Loading

R
RJ Rivera 👤 Member for 21 years 9 months
M
Mohsen Nourbakhsh 👤 Member for 19 years 3 months

the way to go is: Bring up the ’resource usage profile’ then change the timescale setting to show Day/Hour and the histograms will show the actual numbers per day (you will have to compress the bar to get the full duration in a print preview and then print)

A
Arnold Puy 👤 Member for 19 years 1 month

Hi RJ,



You can show your 10 Man-days per day by using the "Spreadsheet Option" & Resource Profile Options --> Calculate Average --> Interval totals by: "10"



This is applicable for Resource Usage Profile/Spreadsheet, Activity Usage Profile/Spreadsheet as well as in the "Resource Assignment".



If you need to do it in Excel sheet then, you can simply use the "Resource Assignment" and change the Timescale to day, week or month. Just copy & paste into Excel.



Note: When pasting into Excel sheet the value will be the same as the original budgeted units.



Regards,



Arnold

Z
Zq qz 👤 Member for 23 years

go to resource loading. and when you generate devide it by 10. to determine mandays.

M
Mike Testro 👤 Member for 20 years 6 months

Hi RJ



P6 must have a labour histogram function somewhere. Every other set of software does.



Best regards



Mike Testro

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts