Problem With schedule Percent Complete
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi Amir,
Schedule % Complete does not roll up in summary band if:
1. The Resources Price/Unit equal to Zero (0).
2. If you assign Baseline to your project, make sure that all resource assignments youve made is the same as that with the current especially "Cost".
3. Make sure that Budgeted Cost for both current & baseline schedule is greater than Zero (0).
Regards,
Arnold