P6-Summery of percent complet

D
Dieter Wambach 👤 Member for 19 years 5 months

Mohammed



you can find those formulas in the Help function, e.g.:



"Schedule % Complete: specifies how much of the wbs’s baseline duration has been completed so far. Computed based on where the current data date falls between the activity’s baseline start and finish dates. If the data date is earlier than the baseline Start, the Schedule % Complete is 0. If the data date is later than the BL Finish, the Schedule % Complete is 100. The Schedule % Complete indicates how much of the wbs duration should be currently completed, relative to the selected baseline." (end of quotation)



There are more %-complete types in P6.



Regards

Dieter

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts