Importing Data form excel sheet into P6
Forum Sponsor
Top Posters
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Thanks so much i did the same it is working fine.
only think while i am importing a new project i mean in new EPS nod it is not working.
during the import i am try to
"modify existing update project"
to new project it also not changing.
while importing it is going in same EPS NOD i want to import under the other EPS nod
Please again advise
Thanks & regards
Shahzad Ahmad
Hi Shahzad,
You are trying to import from Excel to P6 with incorrect format.
Before importing from Excel to P6 make sure that the format came from P6 to Excel then export it back to P6.
Regards,
Hope this helps.
Arnold