Activity completion

R
Ronald Romero 👤 Member for 19 years 7 months

Rohit,



Ask for Extension of time if you cannot mitigate the delay by adding more resources. Or just let it be there are other activities in the critical path that you can reduce duration so that the end of project is as per planned.



Regards,



Ronnie