Progress Resources
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi Alexandre,
Welcome to Planning Planet.
Go to "Assignments" Group them by Resource Name and WBS or Codes then show the "Unit % Complete", "Actual Units" in the column depending on your requirements and manually input the actual units.
If you need to know the % complete for each task then I would suggest to use the Physical % Complete.
Regards,
Arnold