Resource Hours

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Ralph,



Your Remaining Resource Hours always spread in current dates, as long as you did not assign the Future Period Bucket Planning or Resource Curve for each activities.



Current & Planned dates are similar during updating, however, Planned dates ca be updated manually. Try to display/show the Planned Dates on your column and see what happen.



Regards,



Arnold

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts