Importing from P3 to P6
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hello Arnold
Thanks
Hi Sanjay,
Try to change the resource type from labor to nonlabor by filtering all activities having the resource type of labor. Afterwards, select the "Assign Resource" command button located at your right corner of your screen.
Select the resource name and select replace then assign the new resource type (labor). This cannot be done for the activities that has already actual.
Hope this helps.
Regards,
Arnold