updating and resources in P6

B
Brian Yung 👤 Member for 17 years 3 months
D
Dieter Wambach 👤 Member for 19 years 5 months

Brian



When I started with P3 and later P3e the books of Paul Harris didn’t exist - at least not in Germany. I never read them. The opinions I read in PP is that they are excellent and have many good examples.

Update progress using P6 first needs a concept: Timesheets?, frequency, Progress Spotlight (Y/N), duration types, some project-related parameters - especially under the tab "Resources" -, usage of dates ("planned dates"), ...



Together with P6 a training database with many examples is delivered. Install and use it to test new functions.



Good luck!



Dieter

B
Brian Yung 👤 Member for 17 years 3 months

Hi Dieter,



You are right about me starting to use a software without going through a manual first. After I realized that there was more than what I thought involved, I started reading a lot of material. One of them is Paul E Harris’ P6 book which I have gone through.



The only thing that I don’t feel comfortable with is updating the schedule.



Unfortunately I don’t have access to P6 now as my pc is going through maintenance. I will look a the topics that you suggested me.





Thanks,



Brian


D
Dieter Wambach 👤 Member for 19 years 5 months

Anoon

For my opinion Brian started to use a software without training or study of a manual.



Brian

Your questions are related to the usage of a P6.



Please check the following items in the help-function or the ref-manual:



- Autocompute actuals

- View "Projects" detail tab "resources" --> then "F1"

- Usage of "Spotlight"

- Update progress

- View "Activities" --> detail tab "General" --> check for duration type.



Sorry that I didn’t give the answer you expected but I’m convinced that long term this is the better way.



Good luck!



Dieter


A
Anoon Iimos 👤 Member for 19 years 8 months

Hi Brian,



I believe the one who can give best advice on this is Mr. Mike Testro (not to mention C.J.O.). If I may suggest, you break down your activities so as to create always a finish-to-start (FS) link. For example: Your activity "Concrete Pour" can be broken down into the following: 1. Layout -FS-2. Formwork -FS- 3. Reinforcement -FS- 4. Place Concrete. Now you need to define your duration as accurately as possible. Again for example, placement of concrete will take only hours (not days if using pumps).



HTH

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts