In P6 Formating Axis Options are possible.
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi Mohammed,
1. It is possible for Duration % and Cost % complete will be automatically updated if you mark the checkbox next to "Recalculate Actual Units and Cost when duration % complete changes" in Project workspace --> Calculations Tab.
For Physical % complete can either user entered or calculated from the activitys weighted steps.
If you want that Physical % complete will be equal to your Duration % complete, you need to run the global change.
2. It is possible if you will try to change the "Calculate Average" depending in your "Divide interval totals by:" However, the information for your quantity/cost calculation pop-up displayed will also change due to "Calculate Average" you input.
HTH.
Arnold