Regarding (EPC) Engineering, Procurement, Costruction.
Depending on the field, if you were only working to define the Engineering aspect. You would tipically use detail from the engineering department to develop your WBS. Example:
Project Management
Pipeline
Facilities
Hydraulics
Electrical
Survey
ROW
Each department should be able to provide you with details that will help you establish the activities, manhours, expenses needed that will fall under these categories.
Hope this helps you get started.