Exporting from P6 to P5
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi all,
I found out that you will need to use the "Recalculate Cost Assignment" function. That resolved the problem.
Best regards,
Blaise
Hi,
I had a similiar problem, but discovered that there was a currency misalignment. Each project was setup using a different currency and when importing the "budgeted total cost" would show a different amount.
Blaise
Do you know which costs are missing, e.g. related to special activities? materials?
Can you find a criterion?
The Xer file is a text-file. You can read it with the Editor or Notepad. Do NOT use Word or any other word processing software because they would add control characters!
Can you find those costs within the file. The record layout is on your documentation cd.
Good luck!
Dieter