A
A D 👤 Member for 19 years 1 month

I believe, u meant to say, u hav two baselines and both with actual dates in.



Even, in that case, this shud work OR otherwise u can have another workaround without changing the settings in earned value in admin preferences.



Use this global change



AS NE ..... (Blank), then PS EQ AS



AF NE ..... (Blank), then PF EQ AF



Apply these global changes and u can save it as a new baseline and work in a normal way.



Make copies before making global change.

S
Shahzad Ahmad 👤 Member for 18 years 4 months

Hi,Ravi



What will be the case for first time base line update



in Earnd Vaule I have set AT COMPLETION VALUE WITH CURRENT DATE.







THANKS

SHAHZAD

A
Arnel Lagumbay 👤 Member for 17 years 9 months



Thanx a lot Ravi... it works now..simple things seems



difficult without Pps.





Best regards,

Rnel

A
A D 👤 Member for 19 years 1 month

I believe ur actual dates are NOT roped in.



Go to Admin preferences and then click on Earned Value Tab.



At the bottom, select the Budgeted Values with Current dates rather than Planned Dates.



Cheers,



Ravi

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts