Planned % data.

A
Abdul Khadeer 👤 Member for 21 years 9 months

Hi,



You can have planned % weekly only in case if you have loaded your activities with quantities or assigned a resource (by weight loading).



Then you can generate a resource sheet with week on timescale and selecting that resouce.



if your resource is with cost you will get a curve if you go for profile with cost and cumulative options.



Try this.



Cheers

AK