Baseline Importing P6
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi Arnold,
The case I am facing the problem is at the time of
Importing the file to another PC where The Baseline is not
loaded on it.
So, any Idea !!!!
Regards
Hi Riad,
Yes its normal. I am not sure if there is other way of exporting project with baseline.
However, prior to exporting your project restore your baseline first and re-assign it the moment you import the same project.
Arnold