How to Get the Late Curves for the Project
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Shukla ,
You have to used the Time Distributed REport generation .
From where you have to use selection of Time interval fields .
You have to use :
In the Cummulative Units : Drop down list .
Select Cumm Remaining Late Units
and Cumm Remaining Early Units
Hope your surve shall be generated.
Shiv
Hai Friends,
There are lot of posting on this issue but none of them are helpfull to me. In my programme cost is loaded as Expences so I can not use the Resource profile as suggested by Mr.Paul earlier.
The search function of PP are not working so it is not possible to digg old posting on this topic.
ANY HELP FROM ANY CORNER??
Thanks in advance.
A.S.Shukla
Hai Friends,
There are lot of posting on this issue but none of them are helpfull to me. In my programme cost is loaded as Expences so I can use the Resource profile as suggested by Mr.Paul earlier.
The search function of PP are not working so it is not possible to digg old posting on this topic.
ANY HELP FROM ANY CORNER??
Thanks in advance.
A.S.Shukla