Percent Complete inquiry
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Thanks james,
I;ve tried to put some resources on my sample project, unfortunately when I need to get the percentage completion, I have to recompute the total duration and the remaining duration. Is there an easy way where in I can have it viewd on my project. Just to lessen my time for computation.
Thanks in advance, Its really great to be a member of thois forum.
Cheers ! ! !
also, is your schedule fully costed??
Hi James,
Thanks for your reply, ive tried your suggestion, but unfortunately its still the same. Is there any thing I can do with this, I just need to know the Percentage of completion of our project.
Thanks in advance
depends what type of percent complete you are using to monitor progress, if you are using physical % complete then this wont roll up through the WBS levels as you cant compare apples with oranges, try using performance % complete column next to the physical % complete one on your layout, it isnt ideal but it will roll up through WBS levels to the project level