Percent complete issue

J
Jorge Taguinod 👤 Member for 22 years 11 months

This is simple. Been there, done that.



Turn Schedule A into a baseline.

Display Schedule % Complete in your column.



Done. Good huh?

This was not possible in P3!



Cheers



Jorge Taguinod


D
David Podmore 👤 Member for 20 years 1 month

Yep, I concur with Mr K. Load Schedule A as the baseline to B. Or, even simpler if understand the situation; Take A, make a baseline (save a copy of current programme) and thus mark progress against the client programme. No need for a B really.

If you load costs onto A and then baseline you can derive earned value...

D
David Kelly 👤 Member for 21 years 7 months

I have not quite followed what you are trying to do... BUT what is wrong with converting the original project into a baseline?



The "Maintain Baselines" option lets you do this



??

A
Anoon Iimos 👤 Member for 19 years 8 months

depending on the percent complete type you had chosen, update both schedules (A & B) consistently using the same data date

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts