Milestone Activities with invalid relationships?

L
ladi sodipo 👤 Member for 18 years 7 months
G
Garry Macdonald 👤 Member for 18 years 1 month

It happens when you have a finish milestone with a FS relationship to another finish milestone. This should be a FF relationship. Its a similar fix with start milestones etc.

A
Anoon Iimos 👤 Member for 19 years 8 months

it depends if it is a start milestone or a finish milestone, you have to assign corresponding relationship for start and or finish, ask yourself if it is valid to assign a FF for a start milestone?

S
Satya Narayana 👤 Member for 18 years 1 month

If you have FS relationships with in the mile stones this is displayed as invalid relation ship in schedule log/report.



This is one of the cases.

D
Dieter Wambach 👤 Member for 19 years 5 months

Ladi

Don’t worry! For milestones not all relationships are available. If an activity had a different type before you may have assigned an not allowad relation. For scheduling start or finish of a milestone is the same. Until now I never found a susequent error to this one. Just ignore it.

Regards

Dieter

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts