Schedule % complete

J
Jerry Lan 👤 Member for 19 years 9 months
A
Alex Wong 👤 Member for 23 years 4 months

1. Do you remember to move you data date

2. Have you fixed the baseline b4 you add your actuals

3. Have you change (ie add) budgeted unit when you added actuals (its a setting @ project level)



HTH



Alex

A
Anoon Iimos 👤 Member for 19 years 8 months

schedule % complete is based on duration, i.e. days, hours, etc. the accuracy of which depends on how you update your schedule, that means that you have to be consistent, if you use days, then you have to count the actual number of days for each and every activity, or you can make the calculations manually