Calculating Man Hours in P6
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Thank you all for your responses.
It was the type of duration I had assigned. I changed to fixed units/time and it corrected all my activities.
Again thanks!
Beth
Hi Beth
Did you have a look into your user preferences?
Edit --> User Preferences --> Calculations
For better knowledge, then try "Help"
Regards
Dieter
Hi Beth,
Did you try this option: Tools>Recalculate Assignment Costs....
It will help your problem solved.
Duy.
Ken,
Thanks for your response. My only concern is when we made major changes in resources I had to manually recalc and enter the manhours or completely remove and reassign which is very time consuming. And P3 would recalculate itself.
I am thinking P3 was much better.
When you change your resource you might need to manually input the budgeted units / duration / budgeted units/time. When a resource is changed the units somtimes automatically revert to whatever you have as a default setting. Also if you go to the Assignments tab on the tool bar on the left hand side of the screen, it should have a list of all the resources you have in the schedule and their units (you may have to go to the column settings to add the columns that you need).
I hope this helps you out
Ken Barrett
I meant in P5