Remove actuals in P6 (HELP)
Forum Sponsor
Top Posters
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Change Actual Labor Units and Actual Nonlabor Units to zero.
You can do this with a global change, by adding columns, or in the status tab switching between Labor Units and Nonlabor using the drop down arrow:
[[wysiwyg_imageupload:8820:]]
How to de-status a schedule
1. Choose Enterprise, Projects and select the Calculations tab. Choose to "Link Budget and At Completion for not started activities" and "Reset Remaining Duration and Units toOriginal
2. Choose View, Columns and add the columns for Actual Labor Units, Actual NonlaborUnits.
3. Choose Tools, Schedule and set the data date equal to the Project Start Date and schedule.To find the Project Start date, choose Enterprise, Projects. Click on the Dates tab and note the Planned Start date.
4. For the first activity in the list, set the Actual Labor Units to 0. Highlight the activities inthis column and choose Edit, Fill Down.
5. For the first activity in the list, set the Actual Nonlabor Units to 0. Highlight the activitiesin this column and choose Edit, Fill Down.
6. Choose Tools, Global Change and run the 1st Global Change. This will set the Actual Material Units to zero.
7. Run the 2nd global change which sets the activity status to Not Started. 1st Global Change:
Subject Area: Activity Resource Assignments If: Where Resource Type equals Material
Then: Actual Material Units = 0
2nd Global change
Subject Area: Activities If: Where Activity Status is not equal to Not Started
Then: Activity Status Equals Not Started
Hi,
Quick and easy way to remove actuals using only 1 Global Change.
Check out my articel here
https://www.linkedin.com/pulse/quick-way-remove-actuals-from-p6-schedul…
Hi,
I write an article regarding How to remove actual / progress from Primavera P6 schedule.
If you're interested, kindly read it here https://doduykhuong.wordpress.com/2016/08/01/how-to-remove-actual-progress-from-primavera-p6-schedule/
Cheer
here is a link to the detailed instructions on how to do this
http://pmsite.com/forums/viewthread/3064/
Thanks Scott, yeah it worked.PP rocks!
highlight the activity you want to change, go to the status tab, uncheck the finish date, change the physical % complete back to zero, reset the actual & remaining labor units (budgeted quantity)in the labour units box, then you should be able to uncheck the start date, it will ask you Are you sure that you want to change the activity to be Not Started? Jusk click yes and it should work
Hope this helps,
Scott