Baseline of a Baseline
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
On the theme of baselines,
if you agree with the client that the current plan will become the new baseline and it already has performance on it, do you have to do a global change to make the actual/current dates = the planned dates?
Which dates in the baseline does primavera look at for EV?
Cheers,
Oliver
In P5/6 there is ALWAYS a baseline. This because "earned value" can only come from a baseline.
If you unassign all the baselines you have made, then "current project" will be set as the baseline and a baseline bar will still be seen.
All you can do is suppress the baseline bars from showing in the barchart.